I-195 Redevelopment District Building Permit Fee Schedule
Building permit fees for projects in the I-195 Redevelopment District are set at 1.4% of construction costs, inclusive of the fire plan review fee. As required by the I-195 Redevelopment Act of 2011, the state building official issues building permits for projects in the District, however the fee is paid to the I-195 Redevelopment District.
This building permit fee schedule was adopted by the Commission on August 28, 2018.
I-195 Redevelopment District Application Fee Schedule
Projects in the I-195 Redevelopment District must pay an application fee within two days after the Commission grants Final Plan Approval. Application fees are based on the following schedule:
Construction Cost | Application Fee |
---|---|
< $50 million | $25,000 |
$50 million-$100 million | $50,000 |
>$100 million | $75,000 |
This application fee schedule was adopted by the Commission on August 28, 2018.